| STATUS |
Phase |
Action |
Action Nb |
Target |
Achieved |
Version |
|
1
|
Start of work
|
|
|
1993-03-01
|
1994-06-01
|
|
|
2
|
Table of Contents and Scope
|
|
|
1993-11-30
|
1994-12-30
|
|
|
6
|
First complete draft
|
|
|
1997-08-30
|
1997-10-30
|
|
|
7
|
WG approval
|
|
|
1997-11-27
|
1997-11-27
|
|
|
8
|
TB approval
|
|
|
1998-01-30
|
1998-01-30
|
|
|
8 A
|
Draft receipt by ETSI Secretariat
|
|
|
1998-01-30
|
1998-03-11
|
|
|
9 B
|
Start of Public Enquiry
|
PE
|
9833
|
1998-04-17
|
1998-04-17
|
|
|
9 C
|
End of Public Enquiry
|
|
|
1998-08-14
|
1998-08-14
|
|
|
9 D
|
Start of TB review of PE comments
|
|
|
1998-08-28
|
1998-08-21
|
|
|
9 E
|
Draft receipt by ETSI Secretariat
|
|
|
1999-08-30
|
1999-10-04
|
|
|
10 F
|
Start of Vote
|
V
|
9953
|
1999-10-19
|
1999-10-19
|
|
|
10 G
|
End of Vote
|
|
|
1999-12-17
|
1999-12-17
|
|
|
11
|
Vote result determination (adopted)
|
|
|
1999-12-31
|
1999-12-17
|
|
|
12
|
Publication
|
PU
|
|
2000-01-07
|
2000-01-04
|
|